Saint-Petersburg > Business and Economics > Investments > Enterprises Investments > The Settlement of Mozhaisky (Krasnoselsky District)
|
 |
 |
 |
Project № 15 The Settlement of Mozhaisky (Krasnoselsky District) 1.Developer of project: “LENGAS”, the City Gas Company of St. Petersburg, 20, Tchaikovskogo Ul., tel +(812) 273 08 92; info: Anatoly G. MATVEEV; 2.Investment Project “Gasification of the Settlement of Mozhaisky”; 3.Population: current, 735; a future estimate, 735; A connecting gas pipeline (design length) 1/0 km; the (design) length of the outer gas pipelines: 7.6 km; 4. Project efficiency indicator: Estimated cost of project- and construction-and-assembly work: 1.0 million USD. An estimated pay-back period : 6 to 8 years; 5. Sourses of financing structure: investments; 6.Project realization period: 1,5 years; 7.Currently available are: a gas distribution scheme, designing estimates for all the construction-and-assembly works. |
|
 |
 |
| St. Petersburg Administration 191060, St. Petersburg, Smolny |
|  |
|
|
 |







 |
 |
 |
|